This is an LA release that will only be provided to a select number of PLM-sanctioned customers (PDFs only). Contact PLM for details.


IMPORTANT

The SBC 51xx and SBC 52xx platforms are not supported from release 11.0.0 onwards. This release supports the SBC 5400, SBC 7000 and SBC SWe platforms.

 

In an HA configuration, the two SBC Core platforms are connected to each other with the two HA ports using a pair of GigE cables. The connection provides both box-level and port-level redundancy. The HA pair consists of four management ports; two ports each per platform. When switchover occurs, the logical management address follows the currently active server. The packet ports, the MAC and IP addresses float between the HA pair (are replicated from active to standby on switchover).


A logical management address is the IP address associated with a Logical Management IP Interface previously created using EMA or CLI.

See the following pages to configure a Logical Management IP Interface:

Connect HA cables between the HA pair as shown:

Active   HA0<--------->Standby HA0

Active   HA1<--------->Standby HA1


Note

The SBC fails to pair with a machine that is not functionally equivalent in an upward compatibility configuration. During system installation and startup, make sure that the servers are designed to operate together and support full redundancy and high availability. Also, an HA pairing between SBC 5210, SBC 5200, SBC 5110, SBC 5100 and SBC 7000 is forbidden. 

HA Pair Setup between two SBC 5100 Platforms