This section provides an example checklist to prepare a site for the 5210 hardware installation. A similar checklist can be used for other SBC 5000 series hardware.

SBC 5210 Pre-installation Checklist

Task

Notes

Review the guidelines given in the safety recommendations


______________________________________________________________

Site power voltages verified


______________________________________________________________ 

Installation site power check completed


 ______________________________________________________________

Required hardware tools available


 ______________________________________________________________

Additional equipment available


 ______________________________________________________________

5210 received


 ______________________________________________________________

5210 Hardware Installation quick reference received


 ______________________________________________________________

Rack Space/location


 ______________________________________________________________

Distance to Power source/Grounding sources


 ______________________________________________________________

Determining the fuse size


 ______________________________________________________________

Distance to data ports (routers/Switches)


 ______________________________________________________________

Console connectivity (FSP or serial) requirements


 ______________________________________________________________