Use the following pre-installation checklist to prepare a site for the SBC 7000 hardware installation.


SBC 7000 Pre-Installation Checklist


Task

1

Review the guidelines given in the safety recommendations

2

Site power voltages verified

3

Installation site power check completed

4

Required hardware tools available

5

Additional equipment available

6

SBC 7000 chassis received

7

SBC 7000 Hardware Installation quick reference received

8

Rack Space/location

9

Distance to Power source/Grounding sources

10

Determine the Fuse size

11

Distance to data ports (routers/Switches)

12

Console connectivity (FSP or serial) requirements

13

Use a switch/router that supports RFC5227 (for Link Detection support).

NOTE: If switch/router does not support RFC5227, disable probing on Standby port (see SBC Core Redundancy for details).