In this section:
Perform the following tests, at a minimum, after completing the SBC hardware installation to check power redundancy and cabling, as well as test link lights.
Do not test the power redundancy by physically removing a power supply. Never remove a power supply that is powered up.
Accomplish the steps below to perform a power redundancy test.
Accomplish the steps below to verify cabling and link lights.