Overview
Tooltip |
---|
tip | Use ESD protective device |
---|
|
|
systems configured for DC power can accommodate dual redundant DC power supplies, as shown in the following figure.
The DC power supply is a Customer Replaceable Unit (CRU). The product code is SBC-5400-PSUDC.
DC Power Supply
In a dual redundant power supply configuration, the power supplies are hot-swappable. You can replace a power supply without powering down the
platform (provided that one power supply is operational).
Note |
---|
|
Before replacing a power supply in a redundant power supply configuration, verify the status of the redundant power supply. The “POK” LED status must be “solid green”. Removing the power supply when the redundant power supply does not show a solid green status, may cause the system to power down. Contact Customer Support if required. |
SBC 5400 DC Power Supply States
Power Supply Condition | LED States (Green/Amber) |
---|
No DC Power to all PSU | OFF |
DC present/Standby Outputs ON, Main Output OFF | Blinking Green |
Power supply DC Outputs ON and OK | Solid Green |
Main Output Failure (OCP, OVP, UVP) | Blinking Amber |
Fan Fail, OTP, Standby Output OCP/UVP | Solid Amber |
- Electrostatic discharge (ESD) strap
- Replacement DC supply.
- A #2 Phillips-head screwdriver
- Torque driver with #2 Phillips bit
- Voltmeter
Note |
---|
The chassis is shipped with one power supply, unless a second power supply is added at the time the order is placed. |
Note |
---|
To prevent damage from electrostatic discharge, an ESD strap is provided in the accessory kit. Refer to Connecting ESD Wrist Strap to install it. |
Replacing a Power Supply
Perform the following procedure to replace a power supply:
- Attach an Electrostatic Discharge (ESD) wrist strap to the ESD grounding point on the back of the chassis, and place the other end around your wrist (refer to Connecting ESD Wrist Strap, for details).
- Disconnect -48VDC power to the DC power supply being replaced by shutting off circuit breaker or removing fuse on facilities power distribution panel or similar operation.
- Verify the POK LED is off on the DC power supply being replaced.
- Ensure that power is no longer present on power cables using a voltmeter.
Remove clear plastic protective cover on terminal strip.
Disconnect RTN and -48V connections by loosening two terminal strip screws using the #2 Philips screwdriver.
- Disconnect power supply ground connection by removing the screw securing the green chassis ground wire to the DC power supply using the #2 Philips screwdriver.
- Disengage the DC power supply latch by moving the latch to the left.
- Pull on the loop handle to slide the DC power supply out of the SBC chassis.
- Install the replacement DC power supply into the chassis by sliding it forward until the latch clicks in place.
- Reconnect the green power supply ground wire to the DC power supply using the torque driver supply and tighten the screw to 13.9 in/lb.
- Reconnect the RTN and -48V cables to the terminal strip screws and tighten to 13.9 in/lb using the torque driver.
- Reinstall the clear plastic protective cover on the terminal strip.
- Apply power to the DC power supply by turning the circuit breaker or installing the fuse on facilities power distribution panel or similar operation.
- Verify that the POK green LED on the newly-replaced power supply is solid green.
- From the application, verify that no power supply alarms are generated.
CRU Storage
Tooltip |
---|
|
|
All
CRUs are shipped in electrostatic discharge bags and should be handled using appropriate ESD precautions.
The storage environment for these CRUs is:
- Humidity must be less than 95% (non-condensing)
- Temperature must be between -40C and +70C.