Perform the following tests, at a minimum, after completing the SBC hardware installation.

...

Note
This test should only be performed when two power supplies are installed in the SBC
Spacevars
0product
chassis.
Warning

Do not test the power redundancy by physically removing a power supply. Never remove a power supply that is powered up.

...

  1. Verify the MGMT0 and MGMT1 IP ports are cabled and the link lights are green.
  2. Verify the FSP IP port is cabled and the link light is green.
  3. Verify the Media Ports are cabled.
  4. For HA systems, ensure that the HA ports are cabled from Unit 1 to Unit 2, and the link lights are green.

 

Pagebreak