  1. Pull the AC cord or the fuse for DC, for the TOP power supply. Verify that the server retains power. Plug the cord/fuse back in and wait for the power supply LED to be either blinking or solid green.
  2. Pull the AC cord or the fuse for DC, for the BOTTOM power supply. Verify that the server retains power. Plug the cord/fuse back in and wait for the power supply LED to be either blinking or solid green.

Cabling and Link Light Test

...