After installing the SBC 5400 chassis to
chassis in a rack and attaching necessary cables, you are now ready to install power and ground cables and apply power to the
SBC. The SBC 5400 . The is capable of dual redundant AC or DC power.
The standard SBC 5400 standard
platform is shipped with one power supply. A second power supply may be added for redundancy at any time. Please contact your sales representative for more information.
...
Caption |
---|
0 | Table |
---|
1 | SBC 5400 Power Requirements |
---|
|
Configuration | AC Input (W) | DC (W) |
---|
| AC Low Line | AC High Line | Minimum: 90 Vrms Nominal: 100-120 Vrms Maximum: 140 Vrms | Minimum: 180 Vrms Nominal: 200-240 Vrms Maximum: 264 Vrms | Minimum: 40 Vdc Nominal: 48 Vdc Maximum: 60 Vdc | Amps | Watts | Amps | Watts | Amps | Watts | without SBC 5400 without DSP Card | 5.7 | 512 | 2.9 | 516 | 12.6 | 502 | SBC 5400 + 1 DSP Card | 6.4 | 576 | 3.2 | 582 | 14.0 | 559 | SBC 5400 + 2 DSP Cards | 7.2 | 644 | 3.6 | 647 | 14.9 | 594 | SBC 5400 + 3 DSP Cards | 7.8 | 702 | 3.9 | 702 | 17.0 | 678 | SBC 5400 + 4 DSP Cards | 8.5 | 761 | 4.2 | 763 | 17.3 | 692 |
|
...
Anchor |
---|
| grounding_chassis |
---|
| grounding_chassis |
---|
|
Grounding
...
ChassisThe following procedure explains how to ground the SBC 5400 the
platform to local earth using a 7/16 inch wrench:
- Locate the chassis grounding studs on the back of the chassis.
Attach the two hole chassis ground lug PN 300-30016 to the SBC 5400
using two flat washers PN 510-00057, two split lock washers PN 510-00056, and two hex nuts PN 511-00046 as shown in the following figure. Caption |
---|
0 | Figure |
---|
1 | Chassis Grounding Lug Location |
---|
|
|
- Secure the other end of the grounding cable to the earth ground in the building. You can secure the grounding cable to a proper grounding point on the rack, as long as the rack is properly grounded to the earth ground in the building.
...
- Perform a graceful shutdown of the SBC 5400 system through BMC.
- Turn off your local AC power source.
- Remove the power cord.
...
The following procedure explains connecting an SBC 5400 an
power supply to the DC Power and power on the switch. If two power supplies are installed, both need to be connected to power before powering up the switch.
...
In a dual-redundant power supply configuration, the power supplies are hot-swappable meaning that it may be replaced without powering down the SBC 5400 the
platform (provided that the redundant Power Supply is operational).
...
The following procedure explains how to disconnect DC power from SBC 5400 from
chassis :
- Perform a graceful shutdown of the SBC 5400 the system through BMC.
- Turn off the local DC power source.
- Remove the clear plastic terminal cover and set it aside.
- Remove the DC power cables from the terminals, and re-attach the screws.
- Remove the ground cable from the power supply, and re-attach the screw.
...